Works completed this week;

  • Installation of filter drain and outstanding gullies
  • Continued with the new footpath construction on Mill Road roundabout
  • Continued with prepping the road including the final trim type 1 subbase
  • Continued with construction of the flow control manhole
  • Liner to pond 5 installed and started to import topsoil
  • Completed the granite sets on the roundabout
  • Installed the new lamp columns and posts for the permanent signage on Mill Road

Planned works this weekend;

  • Tarmac carriageway 2nd phase & binder to footway
  • Install further road crossing as requested by NG
  • Continue with topsoil works pond 5
  • A full road closure will be in place on both Saturday and Sunday

 

Next week;

  • Continue construction of the roundabout.