Here are the dates of our next part of the High Voltage cable works in Sharnbrook:
17th & 18th March- jointing in Colworth Road
18th March- joint hole on High Street
19th March- pull cable through under Colworth Road
22nd & 23 March Road crossing on High Street for cable under road
25th– 27th March- shutdowns- any outages will be notified to customers by letter.
24th, 26th & 28th– reinstatement of remaining excavations- if not already carried out.
We still have work in Sharnbrook:
To remove cables on Colworth Road gardens and put them in the footway- affecting a few houses (13- 15) who are already aware.
And to remove a supply to the old sewage pump at the A6 end of Mill Road after the electricity abstraction was found. That will be a hole in the highway a day or two before the cable jointing on the 20th & 21st March. Reinstatement to follow within statutory timescales.