Weekly update from the Developers – 18/04/2026

See update of works this week;

Works completed this week;

  • Continued with pond liners and topsoil to attenuation basins
  • Started to install new kerbs to Mill Road and prep the footpaths from Lower Furlong
  • Removed existing tarmac from Mill Road and installed new capping

Planned works this weekend;

  • A full road closure will be in place on Saturday ONLY.
  • Continue with Mill Road footpath and carriageway construction

Next week;

  • Continue with Mill Road footpath and carriageway works
  • Visiting Mill Road residents on Thursday who will be affected by the new footpath and crossovers