Future works by National Grid – advance notice.

Carrying on the reinforcement works from Colworth Road Substation to the entrance of Glebe Rise. It has been agreed with Bedford Highways inspector weekend that working for the road crossings will take place with traffic lights to minimise disruption.

Estimated dates:

· 14-15th Sept. – Road crossing in front of No.12 Colworth Road & the entrance to Glebe rise.

· 16th Sept. – 10th Oct. Excavating from Colworth Road Substation to the grassed area on Glebe Rise.

· 28th & 29th Sept. and 5th & 6th Oct. Carriage way works at the Colworth Rd/Souldrop Rd/High street Junction.

They will have to revisit to complete the joints and shutdown 4th – 6th November.