Site will be closed on Friday 3rd April.
There are scheduled works for Saturday 4th April for the storm water outfall, with the construction of a new headwall which will require a full road closure for Saturday Only. There will also be topsoil movement onsite on the Saturday, along with small plot works by ECL.
Site will then be closed on Sunday 5th April and Monday 6th April reopening on Tuesday 7th April.