Weekly update from the Developers – Friday the 27th of March

Works completed this week;

  • The drainage installation has continued within Mill Road, including the redesign of storm network following the earlier clash.
  • The ducting for the installation of the new electric and fibre has been completed up to the point of connection.
  • Continuation of the kerbs and footpath construction on Mill Road, including the new bus stop.

Planned works this weekend;

  • A full road closure will be in place on both Saturday and Sunday.
  • Continue with footpath construction and drainage works on Mill Road.
  • Earthworks to attenuation basin 5.

Lower Furlong access arrangements;

  • Residents exiting Lower Furlong will not be able to turn left onto Mill Road during the road closure.
  • Right turn access towards the A6 roundabout will remain open.

Next week;

  • Continue construction of the right side of the roundabout.
  • Continue with drainage works to Mill Road.
  • Installation of the headwalls to the attenuation basin 5.