Please see below the weekly update from the developers regarding the work completed this week and what is expected to be done in the coming week
Works completed this week;
- The drainage installation has continued within Mill Road.
- Road crossings have been cut in to accommodate future electric and BT service connections.
- The splitter islands have now been installed.
- Granite set blocks around the roundabout have also been installed.
Planned works this weekend;
- A full road closure will be in place on Saturday and Sunday to allow key surfacing and service works to be carried out.
- Saturday: Tarmac surfacing is scheduled for the left-hand side of the roundabout and the splitter islands.
- Sunday: Installation of road crossings for the electric and BT connections.
Lower Furlong access arrangements;
- Residents exiting Lower Furlong will not be able to turn left onto Mill Road during the weekend closure.
- Right turn access towards the A6 roundabout will remain open.
Next week;
By the middle of next week we expect to:
- Move the Chapter 8 barriers and signage back away from the Lower Furlong junction.
- Relocate the site access to the opposite side of the roundabout.
- Begin construction works on the second half of the roundabout, following the tarmac works carried out on Saturday.
- Site visit scheduled on Wednesday 18th March at 4pm with Paul Pace and Doug McMurdo.