Update for works carried out this week and programme of works for the weekend:
Works carried out w/c 4th May;
- Continue to construct footpath – install PCC edgings and type 1 subbase
- Form driveways and topsoil behind back edging
- Landscaping carried out to roundabout and verge (topsoil rotavated and seeded)
- National Grid completed joint connections and the damaged column replaced by Peacocks
- Binder and surface course to footpaths
Programmed works for the weekend;
- Full road closure for Saturday and Sunday. TM to be removed at the end of Sunday shift
- Plane out and surface course carriageway
- White linining to carriageway
- Remove temp footpaths and reinstate topsoil
- Remove all builders material. Clean and tidy works area
Next week;
- Move heras fence back
- Continue with pond landscaping