Weekly updates from the developers

Update for works carried out this week and programme of works for the weekend:

Works carried out w/c 4th May;

  • Continue to construct footpath –  install PCC edgings and type 1 subbase
  • Form driveways and topsoil behind back edging
  • Landscaping carried out to roundabout and verge (topsoil rotavated and seeded)
  • National Grid completed joint connections and the damaged column replaced by Peacocks
  • Binder and surface course to footpaths

Programmed works for the weekend;

  • Full road closure for Saturday and Sunday. TM to be removed at the end of Sunday shift
  • Plane out and surface course carriageway
  • White linining to carriageway
  • Remove temp footpaths and reinstate topsoil
  • Remove all builders material. Clean and tidy works area

Next week;

  • Move heras fence back
  • Continue with pond landscaping