Hill Farm Phase 2 Consultation
Please see the attached flyer regarding the consultation on Tuesday the 14th of April 2026 from 2:30pm to 6:30pm. Please note that this is not supported or promoted by the Parish Council but we wanted …
Please see the attached flyer regarding the consultation on Tuesday the 14th of April 2026 from 2:30pm to 6:30pm. Please note that this is not supported or promoted by the Parish Council but we wanted …
Site will be closed on Friday 3rd April. There are scheduled works for Saturday 4th April for the storm water outfall, with the construction of a new headwall which will require a full road closure for …
Works completed this week; The drainage installation has continued within Mill Road, including the redesign of storm network following the earlier clash. The ducting for the installation of the new electric and fibre has been completed …
Please see update below on this week’s works, including progress on Mill Road roundabout. Works completed this week; The drainage installation has continued within Mill Road, although an unexpected clash on the storm network was …
Road Closures have advised the contractor has confirmed the following weekends for the Mill Road closures: 14th – 15th March 2026 21st – 22nd March 2026 , 28th – 29th March 2026, 4th – 5th …
Please see below the weekly update from the developers regarding the work completed this week and what is expected to be done in the coming week Works completed this week; The drainage installation has continued …
We have received the following communication from ECL – Sharnbrook – Bellway – 02.03.26 The email from ECL advises: This letter will be distributed today and we will send out further letters during the construction …
Please find attached a copy of the communication from Devcomms. The attached will be hand delivered to the neighbours of the the Hill Farm development, and is being posted here for the benefit of communicating …
The developers have confirmed that they served Commencement Notices on the Council this afternoon for the 1st phases of development works. It is their intention that works will formally start on Tuesday 28th October 2025. …
October 2025 Devcomms have advised that the https://consultwithyou.co.uk/sharnbrook/hillfarm/faq#nav website has been up dated to include the information discussed during the Drop-in session held on the 7th of October 2025. If you have a question not …